GLENMORE TRAIL & SHEPARD ROAD PAVEMENT REHABILITATION

PROJECT OVERVIEW

This roadway rehabilitation project focused on the milling and paving of two major arterial routes — Shepard Road and Glenmore Trail — requiring a strategic approach to traffic management and safety. Given the consistently high volume of commercial traffic, the work was carefully scheduled during off-peak hours and at night to limit disruptions to the public and surrounding businesses. North Star worked in close coordination with the Calgary Police Service to implement phased closures and mobile work zones, ensuring both public and crew safety throughout. The project also included precision adjustments to underground infrastructure elements, executed efficiently during daylight hours to maintain momentum while minimizing impacts on traffic flow. The result was a smooth, coordinated delivery that balanced high-quality roadwork with complex urban traffic demands.

PROJECT DETAILS

Shepard Road SE – $713,000

Asphalt Rehabilitation

  • 2,700m² at 60mm depth – 1,200 tons

  • 10,000m² at 70mm depth – 1,700 tons

  • 4,000m² at 80mm depth – 400 tons

 Adjustments

  • 7 manhole and 11 valve adjustments

Concrete Rehabilitation

  • Remove and replace curb and gutter and driveway crossings along Shepard Place SE

  • Remove asphalt curb at Shepard Place SE and Shepard Road SE; replace with concrete curb and gutter to achieve new grading design

Glenmore Trail (52 Street SE to Barlow Trail) – $2,174,000

Asphalt Rehabilitation

  • 38,100m² at 120mm depth – 7,300t (12.5 HMA)

  • 250m² at 200mm depth – 240t (WB Turn Lane at 52 Street SE) (12.5mm SMA mix)

Adjustments

  • 14 manhole and 7 valve adjustments

Concrete Rehabilitation

  • Remove and replace curb and gutter